Re: Calculation of Automatic Reorder Point

$
0
0

Hi

 

MRP type: VM, Lot size: EX. Planned Delivery Time: 5, Safety stock is 0 (zero)

 

In Forecasting view put below data

Forecast model: D, Historical periods: 1, Forecast period: 1.

In consumption value tab enter data like

10.2015 - 2200 (working days are 22)

 

As per formula (Reorder level = Safety Stock + (per day consumption * Replenishment Lead Time)

ROP = 0 + (100*5) = 500

After executing forecast for month of 11.2015 ( working days of month of 11 is 19) system is calculating ROP is 411.

Now can you explain.

 

Regards

Ashish