Thanks and makes sense.
My current settings is like this on OPU5, looks like in this case my basic start and basic end date will be based on Operation dates, correct?
Also, my scheduling type is "backwards' but I am doing re-order point planning - Now, the system would do forward or backward planning ? thanks